Rosetta Lander Control Center / Commissioning Activities
 
   
 
Lander CVP Activities Time period
Block 1 • Main Subsystems 12.03. - 17.03.2004
Block 2 • Remaining subsystems and Experiments on HPC / CIU main 09.04. - 15.04.2004
Block 3 • Remaining subsystems and Experiments on LPC / CIU red.

Lander internal interference tests

Consert Instrument Clock Drift Correction
16.05. - 25.05.2004
Block 4 • Lander unit combined operation

Lander/Orbiter CONSERT Solar Panel Influence (Pointing Scenario)
03.10. - 05.10.2004
Block 5 • Romap listening to RPC test on Orbiter level (Interference Scenario) 19.10. - 27.10.2004
Block 6 • Lander cruise preparation 27.10. - 28.10.2004